Principal’s Blog: January 2010

Posted by editor on February 10, 2010 under Education and health

It’s 2010 and the countdown begins to the opening in September of the new East Manchester Academy. Principal Designate, Guy Hutchence, continues his monthly round-up…

Despite the frozen start to 2010, work on site continued at a rapid pace. Only one day was lost when the site had to be called because of the freezing conditions in the first week back after new year.

Inside the academy all the rooms are beginning to look the part and a sample room has been fitted out – not unlike a show house – so visitors can get a real idea of what the completed school will be like. Some of the teachers we have recently appointed will come and do some training in school over the February half-term and they’ll get the chance then to familiarise themselves with all the facilities.

The Balfour Beatty Maths Challenge produced some outstanding entries from primary pupils and a VIP tour will be hosted by the contractors on Friday 12th February for the 11 pupils who correctly calculated that 241,248 bricks were required to build the academy! Well done to all who entered, the response was fantastic.

As we move into February, I’m excited at the prospect of appointing our next cohort of staff and finding out in March which pupils have been allocated a place by the local authority. I have been very impressed with the sense of anticipation amongst the youngsters I’ve met so far this term. As soon as we know who will be the very first pupils at the East Manchester Academy we’ll organise ‘transition’ activities so the new pupils will be as familiar with their new school in September as we are.